Schedule performance index (SPI)
The schedule performance index (SPI) is a measure of how close the project is to being completed compared to the schedule.
As a ratio it is calculated by dividing the budgeted cost of work performed, or earned value, by the planned value.
For example:
- A project has a budgeted cost of £120,000.
- According to the schedule, 15% of the project should have been completed after one month (planned value). That is £120,000 x 15 / 100 = £18,000.
- But after a month, only 12% of the project has actually been completed (earned value). That is £120,000 x 12 / 100 = £14,400.
SPI = EV / PV = 14,400 / 18,000 = 0.8
This means that for every estimated hour of work, the project team is only completing 0.8 hours (just over 45 minutes).
If the ratio has a value higher than 1 this indicates the project is progressing well against the schedule. If the SPI is 1, then the project is progressing exactly as planned. If the SPI is less than 1 then the project is running behind schedule.
[edit] Related articles on Designing Buildings Wiki
- Activity schedule.
- Cost performance index (CPI).
- Benchmarking.
- Design programme.
- Earned value.
- Fast-track construction.
- Key performance indicators KPI.
- Lead time.
- Programme for building design and construction.
- Project crashing.
- Scheduling construction activities.
- Time management of construction projects.
[edit] External references
Featured articles and news
Listed despite problems with its design.
Zen and the art of cycling exploration.
Design Council Homes Taskforce launched
To support government 1.5 million homes target within UK climate commitments.
The story of this knowledge quarter building.
In ecology, in hydrology, in biology and in architecture.
Creating environments that promote physical, mental, and social well-being.
UK cases of neutral current diversion
Research project looks for example contributions.
Overstocking and macro-economics cause a decline.
The 2024 update of the Common Assessment Standard
Demonstrating organisational capability’ to fulfil roles under the Building Safety Act.
56 recommendations for a better built environment
Published by the CIC ahead of the King’s Speech.
SkillELECTRIC Top 8 Competitors Named
in annual search for the UK’s best student electrician.
CIOB Diversity and Inclusion technical information sheet
Step-by-step guide on implementing D and I practices.
Conservation and the Indian City. Book review.
Reversibility in conservation ethics
Learning from painting conservation.
Where It's AT Podcast launched!
New CIAT Architectural Technology Podcast goes live.
Comments
Its just 12/15 no need to multiply the percentage by the budget.
Indeed.